I attended the Expo meeting last Thursday. It was very illuminating to hear the challenges involved in the Venice-Sepulveda alignment, though Expo staff were definitely trying to sway opinion against that route. I was beginning to have doubts myself until after the meeting as I tried to figure out a route home. Simply put, aside from the standpoints of costs and ease of construction, the Expo ROW is an inferior route and the Venice-Sepulveda alignment is worth the investment.
Presently, the need for a connection between the Westside and Downtown is distorting the planning for the Expo line. In the absence of the Purple Line, the Expo has been forced to fulfill that transit goal. Consequently, opponents of the Venice-Sepulveda alignment believe it would compromise the regional effectiveness of that connection, slowing it down and diverting it from it route to downtown. I do sympathize with all who express frustration and simply want this line built as quickly and easily as possible. Considering how difficult it has been just to get to this point, I understand how supporters of this line can view any change that raises the cost and complexity as something to strongly resist. However, building an effective transit system is going to require the foresight to look beyond our most immediate needs and anticipate a larger vision for transit. Admittedly, the Expo will initially need to serve as the primary transit connection between Downtown and the Westside. However, what happens when the Purple line takes over for that role? And what about the other transit objectives we need to accomplish, like serving north-south traffic and creating a single transit core for the Westside where all lines converge?
The Venice-Sepulveda alignment has two major advantages over the Expo ROW that justify its greater cost and complexity:
1) Adjacent areas are more appropriate locations for transit service and intensified land usage. Expo staff downplayed the amount of business activity along Venice Blvd, but the scale of commerce along Venice is greatly overshadows the quiet, village-like commercial clusters that line the Expo ROW. Furthermore, there is vastly more empty and under-utilized space for intensified commercial activity along Venice than there is along the Expo ROW. Finally, transit would help Culver City evolve into a much more significant urban center of its own, further feeding the already bustling street life and commercial vitality along Culver Blvd.
2) The infrastructure, while more costly and complex, will be more adaptable and provide more options for future expansion. (a) The Venice segment would establish (along with the Pink line) infrastructure and the alignment that could be later used by a line running from Hollywood to Venice via La Cienega and Venice Blvds. Such a future line (which people are already clamoring for) will be a much easier sell if large parts of it already exist. (b) The Sepulveda segment would orient the Expo towards Westwood. This Westwood orientation is important because although the Expo will initially be connecting Santa Monica to Downtown, if the Purple Line replaces it in that function, the Expo can then be rerouted (sharing the Pink line's infrastructure) up Westwood Blvd to UCLA. The Sepulveda segment could also potentially be used by a line running from the San Fernando Valley down to LAX.
Simply put, the Venice-Sepuveda alignment keeps our options open for future expansion of the system while the Expo ROW simply doesn't. Considering the stop-start nature of transit development in LA, we need to keep our options open even if it is slightly more expensive in the short term. A stitch in time saves nine.
With that, here is my five phase proposal for the construction of the Westside System:
Phase One: Complete Expo line from present Washington/National terminus to Santa Monica via the Venice-Sepulveda alignment.
Phase Two: Build the Pink Line from Hollywood to Santa Monica via Westwood and Pico Blvds.
Phase Three: Extend the Purple Line to Santa Monica via Wilshire.
Phase Four: Reroute the Expo Line to UCLA via Pico and Westwood Blvds.

Phase Five: Construct "Venice-La Cienega" Line using existing infrastructure on Santa Monica Blvd (the Pink Line) and Venice Blvd (the Expo Line).